Process
Seven gates, written deliverables at each one
This is how a STEELWORK package moves from an enquiry to a signed handover. Every stage ends with a document you keep.
-
1
Enquiry and site information
You send drawings, a sketch, or just the plot size and intended use. We ask for the ground report and the loads you plan to support.
Output: budgetary tonnage, indicative RM/t and a programme bar chart
-
2
Structural design
Analysis in the governing code, connection design, and a check against your architect's and M&E's requirements before anything is frozen.
Output: calculation pack and general arrangement drawings for your review
-
3
Detailing and approval
Tekla model is built to LOD 350, clash-checked, then issued as approval drawings. Your sign-off is the gate that opens procurement.
Output: approved GA, connection drawings, anchor bolt plan
-
4
Procurement of steel
Mill selection against your spec, with mill certificates booked at the same time as the section order so traceability is never retrofitted.
Output: mill test certificates, section schedule, cut-optimisation report
-
5
Fabrication
CNC cutting and drilling, fit-up, welding by qualified welders, then blast cleaning and coating to the specified system in an enclosed bay.
Output: assembly drawings, weld maps, DFT and coating records
-
6
Delivery and erection
Load-out in erection sequence, not in alphabetical member order. A lift plan, a method statement and a supervisor on site from the first column.
Output: delivery manifest, daily erection report, survey record
-
7
Handover
Bolt torque checks, touch-up painting, a snag list closed out, and an operation-and-maintenance folder you can hand to your facilities team.
Output: O&M manual, as-built drawings, warranty certificate
Typical programme, 1,000t portal frame
Where programmes actually slip
In our experience the delay is rarely the workshop. It is late approval of the design load assumptions, an anchor bolt plan issued after the concrete is poured, and cladding colour decided on site. We put those three on the critical path in writing at stage two.